Construction has started

Image
Our house is progressing very quickly. Within a month we have had our slab poured, frame delivered and constructed. It is a very exciting process for us.  1. Fencing and toilet delivery  completed date: 20th March 2. Internal drainage  completed date: 27th March 3. Slab completed 2nd of April 4. Framing commenced 20th April