Hebel Completed

Hebel completed

Framing of our house

Image
                                 The framing for both levels of our house is now complete. 

We have a roof!

Image
We have a roof to our home now and we must say it looks great. We are really happy with the colour and how it is looking. Before the roof went on Hebel commenced on the ground floor. We are still waiting for the Hebel on the first floor. Looks like the wait game is on now...                                                                                                                            Monier Roof tiles in Sambuca

Construction has started

Image
Our house is progressing very quickly. Within a month we have had our slab poured, frame delivered and constructed. It is a very exciting process for us.  1. Fencing and toilet delivery  completed date: 20th March 2. Internal drainage  completed date: 27th March 3. Slab completed 2nd of April 4. Framing commenced 20th April

Site Clearance and Tree Removal

Development Approval (DA)

Image
Development Application Lodged:  15 Jan 2020 Development Application   approved:  14 Feb 2020

Electrical Appointment

Electrical Appointment knowledgeable Electrical Consultant took us through all the elements that We can choose for our new home and ensured We tick off all of your requirements.